The reopening of the Pisárek tunnels in Brno after repairs may be delayed: without the client’s knowledge, the contractor asked the regional authority to extend the closure by nine days. The work began in mid-October and was supposed to finish on Nov. 20. This means the daily traffic jams in southwestern Brno will last longer than planned.
“This morning we learned that the contractor asked the regional authority to extend the closure by nine days without our knowledge,” said David Fiala, head of the Brno branch of the Czech Road and Motorway Directorate (ŘSD). According to ŘSD, the modernization could not be put off any longer. The road authority will pay 212 million crowns for the repairs. The Pisárek tunnel has been in operation since 1998.
A coordination meeting of all parties, including the police, the transport company and the city, has been scheduled at the regional authority for Friday. Representatives of the company Eltodo were also invited.
“The work on the technology of both Brno tunnels is in its final stage. Testing of the newly installed equipment has not yet begun. Eltodo will start as soon as ŘSD, as the client, ensures the delivery and installation of electricity meters and the connection of the tunnels to the distribution grid,” said company representative Petr Kovář. According to him, once the connection is made, Eltodo will check the operation of individual devices and then how they work together in complex tests. Nine days should be expected for the safe connection and the necessary tests.
Because of the repairs, long traffic jams form in Brno every day, especially in the southwest of the city. This spot cannot simply be bypassed by letting neighboring streets take the traffic. Public transport has problems, and rescue crews also get stuck in impassable jams.
“The aim of the repair is to keep the tunnels in good technical condition and ensure the reliable operation of the technology systems. Part of the work will also be the repair of the section of the I/23 road that runs through the Pisárek tunnel,” said ŘSD spokeswoman Lucie Trubelíková when the work started. The technology upgrade includes lighting, cameras and detection systems, emergency communications, cabling, power supply and traffic control, among other things.
This affects everyone who travels through southwestern Brno by car or public transport, including foreigners. The Pisárek tunnels have been closed for repairs since mid-October, planned until Nov. 20, but the contractor has asked to extend the closure by nine days.
Around Prague guide on the topic: Christmas markets in Czechia 2026 outside Prague: Brno, Olomouc, Krumlov, Plzeň, dates and hours
Around Prague, based on reporting by novinky.cz