Time-lapse video of highway repairs near Prague's Main Station reveals sluggish pace — Správa železnic explains why

Time-lapse video of highway repairs near Prague

A time-lapse video of repair work on a stretch of the highway near Prague's Main Station, filmed from mid-July to August 3, shows that the construction site stood idle for most of the period. Traffic restrictions on this section due to the reconstruction are planned to last 126 days in total — work is expected to continue until November.

The footage shows that during the first week, up until July 20, almost nothing happened at the site, even though preparations for closing the section were already underway. It wasn't until July 21 that construction equipment arrived on site, with a handful of workers beginning to mill the old asphalt and remove curbs.

From July 23 to 25, the pace remained sluggish: at most one or two vehicles moved around the site, while workers slowly hauled away construction debris and leveled and compacted the gravel base. For hours at a time, machinery simply sat idle. And from July 26 until early August, aside from the occasional vehicle movement, virtually nothing happened in the visible part of the site.

Work was taking place out of the camera's view

According to Správa železnic, the reconstruction schedule is being followed, and the bulk of the work during this period was carried out outside the frame. "The video captures only one specific section and mainly documents the preparatory phase of construction. However, preparations were underway not just in the area covered by the camera, but in many other locations as well," explained Správa železnic spokeswoman Nela Fríbová.

Cheap flights from Prague
One search across every airline and travel agency.
Find tickets
Sponsored

According to her, work was simultaneously proceeding toward Štvanice, preparations were being made to relocate bus stops to Opletalova Street, work was underway inside the station building, and construction beneath the highway itself was being coordinated. In addition, this stage involved preparing the central median strip, which will be needed to switch traffic from one side of the highway to the other during later phases of the reconstruction.

The spokeswoman added that the main construction work began on August 10: removing the asphalt surface, installing a new drainage system, waterproofing, and a new storm sewer system, including new through-holes in the concrete slab.

Source: novinky.cz

Share: Telegram WhatsApp

More U.S. news

Nine Fired FBI Employees Sue Patel and Blanche Over Trump Documents Case Work
Nine former FBI employees sued the bureau, the Justice Department, FBI Director Kash Patel and Attorney General Todd Blanche on Thursday, alleging they were unlawfully fired for their work on the inve
Trump Cancels Livestream Plan for Fort Hood Shooter's Execution
President Donald Trump said Thursday that the planned execution of Fort Hood shooter Nidal Hasan will not be streamed to the public, reversing a plan the Pentagon had floated days earlier. In a Truth
FBI Investigates Suspicious Letters Sent to Senators and State Election Offices
The FBI, the U.S. Postal Inspection Service and U.S. Capitol Police are investigating letters containing suspicious substances that were mailed to congressional offices and state election offices acro
Why Kimberly Guilfoyle Was Asked to Resign as Ambassador to Greece
Kimberly Guilfoyle is leaving her post as U.S. ambassador to Greece after the White House asked her to resign amid allegations of misconduct, according to NBC News and Fox News. She announced the move
Kroger's AI Push: The Numbers Behind 3,000 Planned Corporate Job Cuts
Kroger plans to lay off 3,000 corporate employees over the next three years as it expands its use of artificial intelligence, according to ABC News and Fox Business. CEO Greg Foran announced the move
Supreme Court Will Hear Fight Over Whether DOGE Must Follow Public Records Law
The Supreme Court on Tuesday agreed to hear a dispute over whether the Department of Government Efficiency, known as DOGE, is covered by the Freedom of Information Act. The case could determine whethe

Related news

On Sunday afternoon in Prague’s Dejvice district, a girl of about ten ran onto the tracks in front of an approaching train. The train threw her aside; the child stayed conscious and her life is not in danger.The girl was waiting for the tra
Petr Hlaváček, leader of the STAN movement that won the election in Prague and the candidate for mayor, has admitted that unpopular steps lie ahead for the capital: higher prices for the annual transit pass and resident parking, and the int
An exhibition on the Vltava Philharmonic, the future concert hall for symphonic music in the capital, is under way at the Municipal House on Republic Square in Prague. It can be seen in the centre of the city: on Thursday, 8 October, visito
A truck carrying a drilling rig, travelling along Vídeňská street in Prague at around 9:30 p.m. on Wednesday, got stuck not under the railway bridge but under the neighbouring bridge that carries a metro spur. According to experts, neither
Prague firefighters have freed a truck carrying a drilling rig that was stuck under a viaduct in Krč. At around 11 p.m., they announced on the social network X that after another attempt, using both rescue tanks and an external hydraulic dr
A plan to expand a stone quarry in Prague’s Zbraslav district has met opposition from residents and the local council. In a week, 600 people signed a petition against the project.What the quarry owner saysThe applicant explains the expansio
Prague Zoo has become the first in Czechia to raise an orange-breasted lorikeet chick, a rare parrot that is notoriously demanding to keep. The youngster is now four months old and, according to zoo staff, is a male in good shape.“The paren
At the Trade Fair Palace (Veletržní palác) in Prague, the “Light Workshop” is under way as part of the 28th DesignBlok design and fashion festival: in total darkness, visitors build firefly lamps with the help of blind assistants. The festi
Vyšehrad in Prague has finished repairing the roof of the Basilica of St Peter and St Paul ahead of schedule: the roofing and rafters of the main and south side naves were restored in half the planned time. This was made possible thanks to
From 30 October to 14 November 2026, Prague will host the 34th Alternativa festival of experimental music — one of the city's longest-running showcases of bold, dense sound, running since the early 1990s. The programme is split across two w
In Prague's Smíchov district, construction is in full swing on the most ambitious project in the Czech capital's modern history — a mixed-use quarter rising on what was once an abandoned industrial wasteland. According to the Prague Institu
The STAN movement's candidate for Prague mayor, architect and urban planner Petr Hlaváček, who has spent nearly eight years as deputy mayor for territorial development in Prague's ruling coalition, has unveiled his plan to tackle the capita