The Metro reported delays of more than 60 minutes on the approach, and no reopening time has been given.
The Evening Standard reported five miles of queues on the A2 and a delay of 61 minutes. The west tunnel remains open, but it has a height restriction.
According to National Highways, engineers working on planned overnight maintenance found damage to an expansion joint immediately before the tunnel entrance. The agency said the defect needs emergency repairs to protect the safety of road users before the tunnel can reopen.
The planned works were due to finish at 5am, with the crossing fully open by then. The A282 East Bore Tunnel has instead stayed closed so that repairs can be carried out. National Highways said specialist repair crews were expected to be available on the morning of the closure. The closure will stay in place until the work is finished and the tunnel is confirmed safe.
The Evening Standard reported that specialist workers were on site but that it was still not safe to reopen the east bore.
The Metro said traffic was building for miles back onto the M25 anticlockwise and on the A2, making for a difficult rush hour. The Evening Standard reported that the A2 approaching the Dartford Interchange was congested in both directions.
Traffic is being directed through the west tunnel. It has a height restriction of 4.8 metres (15ft 9in), so taller vehicles cannot use it. The Evening Standard reported that vehicles between 4.8 metres (15ft 9in) and 5.0m (16ft 6in) high are being diverted via the M25 clockwise. National Highways said taller vehicles must use alternative routes.
The Queen Elizabeth II Bridge, which carries southbound traffic from Essex to Kent, is not affected, according to the Metro.
The Evening Standard said around 150,000 vehicles use the crossing every day, and drivers were urged to plan ahead.
The Evening Standard also reported minor delays on parts of London's rail and Tube network that morning, caused by train cancellations and a points failure. These are separate from the tunnel closure.
There is no estimate for when the east tunnel will reopen. National Highways said it would provide further updates as the repairs progress and a clearer indication of the reopening time becomes available.
Read next
What We Know About the Channel Tunnel Minibus-Train Collision That Injured 19
Near-Death Tunnels Come in Black and White, Wide Arches in Color, Study Finds
Crimean Bridge Closed After Reported Ukrainian Strike, Delaying Trains to Peninsula
Around Prague, based on reporting by Metro, Evening Standard
Cover photo: Mike McBey / Wikimedia Commons, CC BY 2.0, cropped