D35 Motorway Through Bohemian Paradise Won't Start Before 2033 — And That's the Optimistic Forecast

D35 Motorway Through Bohemian Paradise Won

Construction of the D35 expressway through the picturesque Bohemian Paradise (Český ráj) region won't begin before 2033 — and even that timeline already looks overly optimistic. That's according to Radek Mátl, director general of the Road and Motorway Directorate (ŘSD), speaking ahead of talks with representatives of the Liberec Region and municipalities affected by the project.

According to him, preparation of the project has essentially started from scratch — the directorate must once again carry out an environmental impact assessment in this ecologically valuable area, a process that will take at least 2.5 years. Construction was originally slated to begin in 2029, then ŘSD documents pushed the date to 2033, but Mátl warns the reality could turn out even bleaker.

"I think this is a very tentative and quite optimistic — if not almost impossible — timeline as things stand. We're unlikely to even settle on a route before 2029. Ahead of us lies 2.5 years of a fresh environmental impact assessment, choosing a variant, then design work and land acquisition. So 2033 is a very optimistic date — I think it'll end up being later than that," the director explained.

A Quarter-Century of Route Disputes

The question of the route and design of the I/35 road, meant to divert transit traffic away from towns and villages and improve the connection between the Liberec and Hradec Králové regions, has been debated for 25 years now. The so-called northern route, spanning 35 kilometers and including an access road to Semily, is written into the territorial plans of both regions. Current estimates put the cost of construction at around 30 billion crowns.

The project lost its environmental clearance after then-Environment Minister Petr Hladík (KDU-ČSL), on his last working day in office last December, revoked a previously issued positive assessment.

Plans called for building the section from Ohrazenice near Turnov to Úlibice near Jičín. The stretch from Ohrazenice to Žernov was to be four lanes, while the section toward Jičín would have two lanes with an alternating third lane. However, according to Mátl, the Hradec Králové Region is now insisting on four lanes along the entire stretch. As a result, a full four-lane motorway option will also be considered, including tunnels demanded by the town of Turnov. "We're ready to include tunnels and, even now, to examine at least a basic version of a major tunnel solution under the Jizera River," Mátl said.

Opponents Push for a Southern Route

Besides the invited mayors and representatives of the Liberec Region, opponents of the project who want the northern route scrapped altogether also showed up at the meeting held at the Střelnice cultural center in Turnov. They favor a so-called southern variant which, according to Jan Piňos of the SOS Český ráj coalition of initiatives, would be gentler on both nature and people, as well as cheaper. "There is no legitimate public interest that would justify routing the road through the heart of Bohemian Paradise. The overwhelmingly dominant interest here is nature conservation," he said.

The southern route would bypass the valuable protected landscape area to the south of Jičín, following roads I/16 and II/268 through Sobotka and Mnichovo Hradiště, steering clear of the core of the Český ráj protected landscape area. However, this would lengthen the journey from Jičín to Liberec and increase the load on the D10 highway. It also wouldn't solve the need for an access road to Semily.

According to Mátl, the southern route isn't included in the municipalities' territorial plans, and the Central Bohemian Region doesn't support this option either. "At this point, such a change simply isn't possible," he noted. If preparation of the southern variant were to begin anyway, construction would have to be postponed by as much as another 20 years.

Source: seznamzpravy.cz

Share: Telegram WhatsApp

Related news

Ontario Premier Doug Ford has sharply criticized US President Donald Trump after his decision to impose 50 percent tariffs on Canadian cars, auto parts and steel starting next year. According to Ford, Trump is underestimating Canadians' wil
Arica, the Chilean city widely regarded as the driest place on Earth, has just experienced unprecedented downpours. Between August 16 and 18, the city received 13.4 millimetres of rainfall — enough to shatter its all-time annual record. Acc
A powerful tornado tore through the Aude department in southern France, between the towns of Carcassonne and Limoux, on Tuesday evening. According to local authorities, 26 people were injured and more than 100 buildings were damaged.The fir
An unusually rainy January this year unexpectedly fuelled summer wildfires across Europe: heavy rainfall triggered explosive vegetation growth, which then turned into perfect kindling once the sweltering heat arrived. Heat, drought and stro
Overnight into Friday, Ukraine struck an oil refinery in Perm, a Russian city located more than 1,600 kilometers from the Ukrainian border. Ukrainian President Volodymyr Zelensky confirmed the attack, writing on X that the strike had hit "d
A video comparing satellite images of the same area in eastern Ukraine, taken on 24 August 2022 and 21 August 2026, has been circulating online. According to the Unian news agency, the difference between the two shots clearly shows how far
On Saturday around 2 p.m., police in the Vysočina Region received a report of a car sliding into the water and slowly sinking. Professional firefighters and a police patrol from Hrotovice, keeping watch from a boat on the water, were sent t
Czech tennis player Markéta Vondroušová, the 2023 Wimbledon champion, has filed an appeal against the four-year ban handed down to her in June by the International Tennis Integrity Agency (ITIA). The punishment stems from her refusal to und
Natalie Harp, the 35-year-old aide to US President Donald Trump, has found herself at the centre of a major scandal after an incident on a golf course in Scotland, where she was seen desperately running after the presidential motorcade. She
České dráhy has won the largest passenger transport tender in Czech history — starting in 2030, the company will operate railway lines in Prague and Central Bohemia for the next 30 years. The contract is expected to be signed in the second
Margarita Floresova (real name Margarita Konovalova), a member of the punk group Pussy Riot, has revealed that Russia's FSB recruited her in 2023 by threatening to kill her relatives, and later ordered her to lure well-known activist Pyotr
The Czech government is preparing a sweeping reform of the tariff pay system for state and public sector employees. According to Labour and Social Affairs Minister Aleš Juchelka (ANO), the changes will affect social workers, staff at cultur